Baseline (locking the original plan)
The baseline stores task dates and planned hours so you can later see schedule slips and scope growth.
- Once the schedule has been agreed with the team, press Capture baseline in the Planning control block.
- From then on, the Baseline vs actual section shows: Tasks slipped vs baseline, Tasks with expanded scope, Baseline hours and Current plan / actual.
- The Baseline shifted and Scope increased badges appear in the task list and in the Gantt chart.
When should I capture a new baseline?Only when leadership has formally approved the revised plan. Otherwise you lose your point of comparison.
Milestone approvals
- Enter the Milestone title and End date.
- Optionally, choose a Related task and add a Description.
- Press Add.
- The approver adds Approval notes and presses Approve or Reject. The system records the approver and the time.